A 200 MW HVDC link between two radial distribution grids in Vermont and Quebec. In April 1984 ABB received a contract for the supply of a 200 MW back-to-back HVDC converter station to Vermont Electric Power Company (VELCO). An extremely short delivery time of 17 months was required, and the station was taken into service in September 1985. An agreement had been reached between the State of Vermont and Hydro Quebec about the import of electric power, since it was planned to shut down the Vermont Yankee