Sitemap
Login
A
A
A
Home
About ABB
Products & services
News center
Careers
Investor relations
Offerings A-Z
ABB Product Guide
Industries and utilities
Service Guide
Contact Directory
Power Transmission and Distribution
Flexible AC Transmission Systems
HVDC
Network Management
Power Systems Consulting
Service
Substations
Substation Automation and Protection
Utility Communication Solutions and Products
Downloads
Espoo webcam pictures
HVDC
>
HVDC References
>
Europe
>
Estlink HVDC Light
>
Webcam
Espoo Webcam - Follow the construction of a HVDC Light station from February to November 2006!
2006
November 30
Four days before the inauguration.
October 31
The first snow.
October 19
No outdoor work. The plant is made ready for connection to the AC grid.
October 9
Last part of the roof in place.
October 5
Phase reactors being lifted into the building through the opening in the roof.
Sepember 11
The main action is going on inside now. Not much of outdoor work.
Sepember 1
Valve cooling and station power module.
August 24
Indoor picture
Various civil works and installation activities.
AC side.
August 18
Indoor picture
Various civil works and installation activities.
DC side.
August 14
Indoor picture
Various civil works and installation activities.
DC side.
August 7
Various civil works and installation activities.
August 1
Various civil works and installation activities.
July 26
Construction work on building roof and walls.
July 21
Construction work on building roof and walls.
July 17
Valve coolers beeing mounted.
July 14
Building partly roofed.
July 2
Transformer arriving.
June 28
IGBT valve enclosures placed on top of enclosures for control and valve cooling.
June 14
Steel pillars for the building
June 6
Work on building foundation
May 30
Work on building foundation
May 22
Preparing building foundation
May 17
Preparing cooler foundation
May 10
Preparing cooler foundation
May 2
Shingle filling.
April 24
Shingle filling.
April 17
Concreting foundations.
April 6
Concreting foundations.
March 31
Site preparation. Concrete moulds are set up.
March 24
Site preparation. Piling for foundations.
March 17
Site preparation. Piling for foundations.
March 13
Site preparation. Piling for transformer foundations.
March 06
Site preparation.
February 21
Site preparation.
Last edited 2009-09-25
Search
Products & Services only
Search
Rate this page
Select rating:
1
2
3
4
5
1 = Poor
5 = Excellent
Your comments:
E-mail / contact information (optional):
Cancel
E-mail this page
1. Your e-mail address:
2. Send to e-m
ail address:
3. Your personal note:
Entering HTML code in the message is not allowed. Please do not use the < or > characters in your message.
Cancel
gad02181 76f5e6d935af804ec125711e002a138f