Iron Ore Beneficiation Plant Gol-E-Gohar

Client

National Iranian Steel Company, Tehran, Iran

ProjectGOL-E-GOHAR & EXTENSION

Capacity2.75 Million t/y of Fe concentrate

BackgroundThe iron ore is taken from the mine (5 Mt/y) to the plant where it is beneficiated in 3 parallel process lines.

ConsultantDavy McKee, Canada (Lines I & II)
Namvaran, Iran (Line III)

Process EquipmentVoest Alpine Industrieanlagenbau, Austria

Scope of ABBDesign, manufacture, delivery to site, erection supervision, testing and commissioning of:

20kV and 6kV Switchgear
Distribution Transformers
Low Voltage Switchgear and MCC’s
MV and LV Motors and Drives
MV & LV Power factor correction equipment
Process Control System
Instrumentation

Award of contract1989 (Extension 2000)

Start of Operation1993 (Extension 2003)


Last edited 2003-10-23