Delivery Times for Components (Ludvika, Sweden)

Standard delivery times from ABB AB, Components. Valid for delivery ex works Ludvika after full and firm order.

Our ambition is to update the delivery times on a weekly basis to reflect our actual load situation. We still have to reserve ourselves for large orders received during the period in between, which might make the actual delivery time longer. It might be possible to deliver a few units in shorter time - please contact us for more information.

Bushing delivery times are applicable for standard bushings with brown insulators.
GSA delivery times are applicable for grey insulators and standard shed profile.

Final delivery times are always as per the order acknowledgement.

For bushings marked "on request", contact your local sales responsible.


Present preliminary delivery times
Updated 2009-11-18
Tap-changers
UBB..7 weeks
UZ...7 weeks
UCG..7 weeks
UCL..7 weeks
UCC..13 weeks
Bushings
GOB 250 to 4507 weeks
GOB 550 to 6507/12 weeks
GOB 75012 weeks
GOB 105023 weeks
GOE 250 to 45027 weeks
GOE 650 to 1175, and GOE(2) 117523 weeks
GOE 1300 to 2550, and GOE(2) 1425 to 1675on request
GOEK 1050-142524 weeks
GOEK 1675on request
GOH7 weeks
GOM23 weeks
GSA-OA18 weeks
GSB 245on request
GSB 362 to 55025 weeks
GSBK20 weeks